Total project time is the shortest project time in which the project can be completed.(a) True(b) FalseThe question was posed to me during an internship interview.The above asked question is from Developing a Network topic in chapter Planning of Building and Colony of Civil Engineering Drawing

Answer»

The CORRECT option is (a) True

Explanation: This is determined by a SEQUENCE of activities and known as ‘’Critical PATH’’. Activities which are not on the critical path are important but not critical akin to the activities falling within the critical path.