1.

___________ is defined as a job or action to be completed, between two events within a project.(a) Planning(b) Event(c) Activity(d) SequenceThe question was posed to me during a job interview.My question is taken from Developing a Network in section Planning of Building and Colony of Civil Engineering Drawing

Answer»

Correct option is (c) ACTIVITY

The BEST explanation: The activity CONSUMES time and money and is represented by an arrow indicating the sequence in which the events occur. Each activity is independent, and indicates such work as preparation of designs, scrutiny of tenders, laying of pipes, foundations, erections of FRAME, INSTALL mill work etc.



Discussion

No Comment Found

Related InterviewSolutions