Critical path is represented by a thin line indicates the line of sequence of activity which must be completed on schedule.(a) True(b) FalseI had been asked this question by my college director while I was bunking the class.The doubt is from Developing a Network topic in chapter Planning of Building and Colony of Civil Engineering Drawing |
|
Answer» CORRECT answer is (B) False The explanation is: Critical PATH is represented by a thick line INDICATES the line of sequence of activity which must be COMPLETED on schedule. |
|