Once a project is planned in terms of ‘events’ and ‘activities’ what next is important?(a) Schedule(b) Activity(c) Time(d) FinishingThis question was addressed to me at a job interview.Origin of the question is Developing a Network topic in chapter Planning of Building and Colony of Civil Engineering Drawing

Answer»

The correct choice is (a) Schedule

The explanation: Time required for COMPLETING each JOB has to be fixed with reference to attainable FACTORS. A too short time or a too LONG time will prove unrealistic. Time duration has to be fixed with reference to experience, general AVAILABILITY of men and materials and completion of procedures.