When a project has too many structures then it is prepared separately keeping in view the whole, and a combined critical path of the whole project is prepared linking one another.(a) True(b) FalseThe question was asked in semester exam.I would like to ask this question from Developing a Network in section Planning of Building and Colony of Civil Engineering Drawing |
|
Answer» Right choice is (a) True |
|