When a project has too many structures then it is prepared separately keeping in view the whole, and a combined critical path of the whole project is prepared linking one another.(a) True(b) FalseThe question was asked in semester exam.I would like to ask this question from Developing a Network in section Planning of Building and Colony of Civil Engineering Drawing

Answer»

Right choice is (a) True

Explanation: The critical path of the whole combination gives a complete picture of the whole project at a GLANCE and HELPS the management to detect and to locate the bottlenecks of different works under different organisations and under different agencies and to TAKE remedial actions well in ADVANCE and to exercise an OVERALL control.